Visit of Sh. Y. K. Chaubey, Director(Technical), NHPC Ltd to CVPPPL Projects 10-Mar-2021
Director (Technical, NHPC ltd & Member of CVPPPL Board, Sh Y.K.Chaubey visited CVPPPL Projects located in District Kishtwar, J&K on 10.3.2021 & 11.3.2021. During the visit, he was accompanied by Sh. A.K.Chaudhary, MD, CVPPPL, Sh Kesav Desmukh, ED(D&E), NHPC ltd, Sh Rajan Kumar, CGM (RO, Jammu) , NHPC ltd along with Sr officers of CVPPPL.
Sh Y.K. Chaubey, visited Kiru H.E project on 10.3.2021 and took a stock of progress of works of ongoing work fronts like Diversion tunnel, MAT, APST, VT & Dam site. He lauded the efforts of CVPPPL in day lighting the Diversion tunnel ahead of schedule and advised to maintain the tempo to divert the River soon after ensuing monsoon season to start Concrete Dam works. On way to Power House site of Pakal Dul Project, Sh. Chaubey took a view of locations of major components of Kwar H.E Project. During visit to Power House site of Pakal Dul H.E Project, Sh Chaubey reviewed progress of works of Power House Cavern, Transformer Hall cavern, Bus Ducts, Approach road to Surge Shaft top, Surge Shaft Road tunnel, Valve House, HRT-TBM platform area and advised to put in more efforts to complete the activities within stipulated time frame.
On 11.3.2021, the Dam site of Pakaldul H.E project at Drangduran was visited by the dignitary, during which progress of works of Diversion tunnel inlet portal, invert lining of DT, surface spillway, tunnel spillway, Intake were reviewed.
During the visit, Sh Chaubey interacted with respective executing agencies of works packages and advised to ensure completion of works as per schedule.