सीवीपीपी (पी) लिमिटेड (एनएचपीसी और जेकेएसपीडीसी का एक संयुक्त उद्यम) की परियोजना पकल दुल एच.ई. (1000 मेगावाट) में राइज बोरिंग मशीन का उपयोग करते हुए 291 मीटर डीप वर्टिकल प्रेशर शाफ्ट के पायलट होल की बोरिंग का प्रारंभ। 16-Jul-2021
Boring of pilot hole of 291m deep vertical Pressure Shaft of Pakal Dul H.E. Project (1000 MW) being executed by CVPP(P) Limited (A joint venture of NHPC and JKSPDC) commenced successfully as per schedule on 16th July, 2021 in the presence of Sh. A.K. Choudhary, Managing Director & Senior Officials of CVPP(P) Limited using state of the art Raise Boring Machine. Pakal Dul H.E. Project envisages construction of 4 nos. 291m deep, 3.9m diameter Pressure Shafts for transmission of water from HRT to Powerhouse. Commencement of boring of vertical Pressure Shaft is an important milestone towards successful commissioning of the project as per schedule.